Week 2
Due Sat: Process book layout
Week 3
Due Tues: Research for scenery – buildings, trees, props, ect.
Due Thurs: Thumbnail warm ups – create sketches of research x 25-50
- Process book Update
Due Sat: Out of the research choose an environment to work with
Week 4
Due Tues: Thumbnails of chosen environment x25-50
Due Thurs: Sketches of environment x25-50
- Process book Update
Due Sat: Pick 10 Sketches and do color tests on them “looking for flow, consistency, and feel”
Week 5
Due Tues: The color of the environment is picked, 2 scenes for the project are picked
Due Thurs: Project Review One – Scene 1 completed, scene 2 started
- Process book Update
Due Sat: Scene 1 & 2 completed and mounted “Black foam core”=)
Week 6
Due Tues: Research for weapons – guns, grenades, ects
Due Thurs: Thumbnail warm ups – create sketches of research x 25-50
- Process book Update
Due Sat: Out of the research choose weapons to work with
Week 7
Due Tues: Thumbnails of chosen weapons x25-50
Due Thurs: Process book Update
Due Sat: Sketch of weapons x25-50
Week 8
Due Tues: Project Review Two - Pick 10 Sketches and do color tests on them “MW2 have different skins for each weapon”
Due Thurs: Process book Update
Week 9
Due Tues: Model sheets of weapons
Thurs: Process book Update
Due Sat: Process Book done, printed and in folder /w CD
Week 10
Due Tues: Formal Presentation of Final Project & Process Book
Due Thurs: Post-Mortem